Friday, December 27, 2013

Railways to Commission Khanapur-Humnabad New Rail Line & Flag Off Humnabad-Bidar DEMU Passenger Train

Shri Mallikajun Kharge, Honorable Minister for Railways will commission Khanapur-Humnabad New Rail Line (Part of Bidar-Gulbarga New Rail Line Project) & flag off the inaugural Humnabad-Bidar DEMU Passenger Train at a function to be held at Humnabad Railway Station  at 11:30 am on Sunday, the 29th  December, 2013.

The function will be held in the august presence of Shri Dr. N. Dharam Singh, Honorable Ex. Chief Minister of Karnataka & Member of Parliament (Bidar), Smt. Umashree, Honorable Minister for Women & Child Development, Kannada and Cultural Department and District In-charge Minister (Bidar), Govt. of Karnataka. Other Honorable public representatives concerned,  dignitaries and senior railway officials will also participate in the function.

The inaugural run of the DEMU Passenger on its flagging off will depart from Humnabad Railway Station at 11:30 hrs on 29th December, 2013, depart Nanagaon at 11:44 hrs, Hallikhed at 12:06 hrs, Kanaji at 12:23 hrs, Khanapur at 12:42 hrs and arrive Bidar at 13:15 hrs on the same day.

Regular Train services on this section will commence form 30th December, 2013.  South Central Railway will run three DEMU Passenger trains between Bidar and  Humnabad  and three DEMU Passenger trains  in the return direction between Humnabad and Bidar as per the following schedule:- These train services will  run on all days of the week except on Thursdays and Sundays.

1)Train No.77651 Bidar-Humnabad DEMU Passenger train will depart Bidar at 05:00 hrs Khanapur at 05:20 hrs, Kanaji at 05:38 hrs, Hallikhed at 05:55 hrs, Nandagaon at 06:16 hrs. and arrive Humnabad at 06:45 hrs on the same day.

2) Train No. 77653 Bidar-Humnabad DEMU Passenger train will depart Bidar at 13: 30 hrs Khanapur at 13:50 hrs, Kanaji at 14:08 hrs, Hallikhed at 14:25 hrs, Nandagaon at 14:46 hrs.and arrive Humnabad at 15:15 hrs.  

3) Train No. 77655 Bidar-Humnabad DEMU Passenger train will depart Bidar at 18:00 hrs Khanapur at 18:20 hrs, Kanaji at 18:38 hrs, Hallikhed at 18:55 hrs, Nandagaon at 19:16 hrs.and arrive Humnabad at 19:45 hrs.

4) Train No. 77652 Humnabad-Bidar DEMU Passenger train will depart Humnabad at 07:30 hrs,   Nandagaon at 07:44 hrs, Hallikhed at 08:06 hrs, kanaji at 08:23 hrs, Khanpur at 08:42 hrs and arrive  Bidar at 09:15 hrs on the same day.

5) Train No. 77654 Humnabad-Bidar DEMU Passenger train will depart Humnabad at 15:30 hrs,  Nandagaon at 15:43 hrs, Hallikhed at 16:05 hrs, kanaji at  16:22 hrs, Khanpur at 16:40 hrs. and arrive  Bidar at 17:15 hrs on the same day.

6) Train No. 77656 Humnabad-Bidar DEMU Passenger train will depart Humnabad at 20:00 hrs,  Nandagaon at 20:13 hrs, Hallikhed at 20:35  hrs, kanaji at 20:52 hrs, Khanpur at 21:10 hrs and arrive  Bidar at 21:45 hrs on the same day.

Wednesday, December 26, 2012

BANIHAL-QAZIGUND RAIL LINK


Northern Railway is going to achieve o­ne more milestone in Jammu & Kashmir State in transportation sector with the completion of Banihal-Qazigund section of Udhampur-Baramullah-Srinagar Rail link Project. Trials have been started in the section by Railways with the arrival of first Track Tamping machine at Banihal o­n 24.12.12 from Qazigund. All the major works have been completed and finishing touch is being given. This section will be ready for opening shortly. The total expenditure of Rs. 1691.00 Crores has been incurred by the railways to complete this section.

Banihal-Qazigund section is 17.729 Kms long out of which 6.514 Km portion is o­n cutting and embankment including bridges and 11.215 Kms is through tunnel. About 11, 78,500.00 cubic meters of earthwork in cutting and filling has been done. The maximum depth of cutting is 15.20 meters and maximum height of embankment is 16.70 meters. 39 nos. of bridges have been constructed in this section which include two major bridges, 30 nos. of minor bridges and 7 nos. of ROBs/RUBs.

The section consists of o­nly o­ne tunnel i.e. Pir Panjal Tunnel which is 11.215 Km long. This tunnel is longest transportation tunnel in India and second longest in Asia. The tunnel has been constructed with total cost of Rs.1300.00 Crores. Almost seven years have been taken by Railways to complete this tunnel. About 7,500 Metric Tonnes of steel, 3, 28,000 cubic meters of concrete has been used and  10,00,000 cubic meters of underground excavation has been done to complete the tunnel. 1300 workers and 150 engineers worked round the clock to accomplish this challenging task.

In order to expedite the work o­n this tunnel by creating more working faces, o­ne Adit of 772.00 meter length and o­ne Shaft of 56.00 meter depth and 11.00 meter diameter was constructed. The tunnel has been constructed by NATM (New Austrian Tunnelling Method) which was firstly used o­n such large scale in India. This method optimizes the tunnel design by mobilizing the inherent ground strength in adopting a curved section, providing primary support system immediately after the excavation and monitoring the ground behaviour while permitting it to develop its inherent strength. Maximum overburden o­n this tunnel is 1100 meters and bore holes up to 640 meters depth were drilled for Geotechnical investigations. A 3.0 meters wide road has been provided inside the tunnel for maintenance, emergency rescue and relief operations. The tunnel has been made water proof by providing continuous PVC membrane between primary and secondary lining. The tunnel has been equipped with the State of the Art air quality monitoring system, ventilation system, communication system, fire fighting system and emergency rescue system in case of emergency. Ballastless Track system has been provided inside the tunnel which is pollution and maintenance free with very good riding quality. By adoption of these systems, Pir Panjal tunnel will be totally dry, pollution free, safe, comfortable and completely illuminated.

Opening of Banihal-Qazigund railway section will be a turning point not o­nly in the history of Jammu & Kashmir State o­nly, but for the Indian history.  A lot of problems are being faced by passengers travelling between Banihal and Qazigund due to closure of Jawahar Tunnel in winter season owing to heavy snow fall. All these problems will be reduced to a large extent by running of train services between Banihal-Qazigund.  Moreover the distance between Banihal and Qazigund will also be reduced from 35 Km road length to 17.729 Kms railway line. It will be a cheaper, faster and dependable mode of transport.